Interim Housing at Canalino, CMS and CHS
During Summer 2017, interim housing projects were completed at Canalino, CMS and CHS. With interim housing in place for student and staff use, existing portables were demolished, and staging and site work was completed for future modernization projects as well as the construction of the …
Carpinteria Middle School Art & Shop Building Roof Replacement
The Art and Shop Building was re-roofed in Summer 2017. Channel Islands Roofing was selected as the contractor. The project was under budget and cost $181,423.
Carpinteria High School Classroom Wings B & F Roof Replacement
The roofs on Classroom Wings B and F were replaced over Summer 2017. Through a competitive bid process, Santa Barbara-based Derrick’s Roofing Company was selected as the contractor.
Carpinteria High School Upper Gymnasium roof replacement
The roof on the Upper Gymnasium is being replaced and includes repairing and/or replacing the existing skylights as necessary. Inside the gymnasium, new motorized basketball backstops are being installed to automate the raising and lowering of all of the existing basketball backboards. Contractor: Derrick’s Roofing …
ADA Site Improvements – Walkway Replacements Phase 1 at Carpinteria High School
The project made ADA improvements to the site by replacing a portion of the walkways on campus. This included underground utility work on the associated gas, electric and sewer lines. Construction Cost: $562,726 Contractor: Shaw Contracting
Carpinteria High School Classroom Wings C and G and Upper Gym Roof Replacement
The roofs on Classroom Wings C and G and the Upper Gymnasium were replaced and included repairing and replacing the existing skylights. Construction Cost: $503,912 (Wings C & G) Contractor: Craig Roof Company Construction Cost: $138,237 (Upper Gym) Contractor: Derrick’s Roofing Company
Multipurpose Building Roof Replacement at Carpinteria Middle School
The project replaced the roof on the existing Multipurpose Building and included repairing and replacing the existing skylights, as necessary. Construction Cost: $176,087 Contractor: Channel Islands Roofing, Inc.
Multipurpose Room Interior Upgrades at Canalino Elementary School
The project included painting the interior of the multipurpose room (cafeteria area) and its entrance vestibule and installing new flooring and new wall-pocket folding lunch tables and benches. Construction Cost: $223,700 Contractor: EJS Construction, Inc.
Replace student lockers at Carpinteria High School
A total of 860 new lockers were installed at Carpinteria High School in January 2016. The lockers have a superior paint coating system that will be easier to maintain, continuous stainless steel hinges for long lasting durability and are also ADA compliant. New locks with …