  • Measure U Summer 2016 Projects Underway

    CUSD Keeps it Local with Carpinteria-based Contractors

    CARPINTERIA – The Carpinteria Unified School District has broken ground on five projects funded by Measure U; the general obligation bond generously passed by the voters of Carpinteria and Summerland for facilities improvements. These five projects are categorized as “quick start” projects and are anticipated to be completed by the time the students return to school in late August.

    • Canalino Elementary School – Multipurpose Room Interior Upgrades
    • Carpinteria Middle School – Multipurpose Building Roof Replacement
    • Carpinteria High School – Roof Replacement for Classroom Wings C & G
    • Carpinteria High School – Roof Replacement for Upper Gymnasium
    • Carpinteria High School – ADA Site Improvements – Walkway Replacements Phase 1

    Unlike most of the other Measure U projects that are larger and more complex, “quick start” projects do not require approval from the Division of the State Architect and can be constructed during the summer months. The selection of these projects is based solely on that criteria. It is of utmost importance to CUSD to keep campuses safe and operational throughout the life of Measure U. Whenever possible, it is the District’s intent to take advantage of implementing projects during down-time when staff and students are not on campus.

    Contractors are hard at work to complete these projects over the next few weeks. Of the five contractors selected, two of them – Shaw Contracting, Inc. and EJS Construction, Inc., – are Carpinteria-based companies and both owners, Jeff Shaw and Paul Sanchez, respectively, are CHS alums. Superintendent Micheline G. Miglis stated, “We’re thrilled to award nearly 50% of the total construction contracts for this round to firms right here in Carp, putting the community’s tax dollars back into the local economy. The fact that these are two of our own is very gratifying.” The remaining projects were awarded to companies located in Santa Barbara and Oxnard.

    “These five projects, totaling $1.5 million in construction costs, represent the beginning of a long line of tangible and visible outcomes of the first bond issuance of Measure U,” said Micheline G. Miglis, Superintendent. “We look forward to sharing this with our community, without which none of this would be possible.”

    Please note: Carpinteria Unified School District awards construction contracts to the lowest responsible bidder utilizing an open, competitive process as required by Public Contract Code.

    Description of Summer 2016 Projects

    CANALINO ELEMENTARY SCHOOL
    MULTIPURPOSE ROOM INTERIOR UPGRADES

    The project includes painting the interior of the multipurpose room (cafeteria area) and its entrance vestibule and installing new flooring and new wallpocket folding lunch tables and benches. Contractor: EJS Construction, Inc.

    Construction Cost: $223,700

    CARPINTERIA MIDDLE SCHOOL
    MULTIPURPOSE BUILDING ROOF REPLACEMENT

    The roof on the existing Multipurpose Building is being replaced and includes repairing and/or replacing the existing skylights as necessary.

    Contractor: Channel Islands Roofing, Inc.

    Construction Cost: $177,874

    CARPINTERIA HIGH SCHOOL
    ROOF REPLACEMENT FOR CLASSROOM WINGS C AND G

    The roofs on Classroom Wings C and G will be replaced and includes repairing and/or replacing the existing skylights as necessary.

    Contractor: Craig Roof Company

    Construction Cost: $499,120

    CARPINTERIA HIGH SCHOOL
    UPPER GYMNASIUM ROOF REPLACEMENT

    The roof on the Upper Gymnasium is being replaced and includes repairing and/or replacing the existing skylights as necessary. Inside the gymnasium, new motorized basketball backstops are being installed to automate the raising and lowering of all of the existing basketball backboards.

    Contractor: Derrick’s Roofing Company

    Construction Cost: $134,000

    CARPINTERIA HIGH SCHOOL
    ADA SITE IMPROVEMENTS; WALKWAY REPLACEMENTS PHASE 1

    The project will make ADA improvements to the site by replacing a portion of the walkways on campus outside of Classroom Wings C & G. This includes the underground utility work for the associated gas, electric and sewer lines.

    Contractor: Shaw Contracting, Inc.

    Construction Cost: $509,000